County Highway 19 & County Highway 38 Improvements

 In Announcements2

Highway Department Provides Update on County Highway 19 & 38 Road Project

The Wright County Highway Department has posted an update to the progress on the County Highway 19 & 38 road improvement project. The update includes a map of the Stage 1B detour with a timeline, project background, an aerial map of the project layout, project visualizations, a story map and contact information for both the Wright County Highway Department and the consultant designer. It can all be found at www.csah19.com.

 

Update regarding the construction progress on the County Highway 19 & 38 Project

The project will be entering the next phase of Construction starting August 3rd. The following is a breakdown of proposed scheduling and Traffic Detour plans.
Mid afternoon Monday August 3rd CSAH 19 from Lamplight Drive north to 70th Street will be closed. At that time traffic from the I-94 ramp North to Lamplight will have access to all businesses along CSAH 19. There will be a local business detour from Lamplight to 67th to provide access to Slumberland and Welcome Furniture. A detour will be in place for approximately 8 weeks. This detour shall utilize CR 37, MacIver and CR 38 for North Bound and South Bound 19 traffic as outlined in black below.

 

Road construction, including road closures and detours, starts 4/13/20.