CITY IMPROVEMENT PROJECTS

 In Announcements2

Wastewater Treatment Plan(WWTP)-Forcemain Improvements
At the WWTP, crews are working on the new storage tank.  The city is getting pricing to update the main lift station at the plant as part of the project, which would include new pumps and hardware.

The forcemain pipe has been placed along CSAH 19 and 70th Street NE.

CSAH 19 and CSAH 38(70th Street NE) Improvements
The project is currently being re-bid and bids are expected to be opened in late November.

 

 

 